Winery Wind 1 Installs First 853-Foot-Tall GE Haliade-X Wind Generators


We hear quite a bit about offshore wind installations that have been halted because the financial calculus modified, rendering among the initiatives unprofitable. Little, although, is being stated concerning the ahead progress with Winery Wind 1 off the coast of Massachusetts.

In October, the primary of sixty-two 853-foot-tall GE Haliade-X Wind Turbine Mills was put in on website. Its nameplate capability is 13 megawatts, able to offering energy to greater than 6,000 properties and companies in Massachusetts. It’s a first-in-the-nation “tax fairness package deal for industrial scale offshore wind.”

Winery Wind is presently constructing this primary utility-scale offshore wind power undertaking over 15 miles off the coast of Massachusetts. The undertaking will generate clear, renewable, inexpensive power for over 400,000 properties and companies throughout the Commonwealth, whereas decreasing carbon emissions by over 1.6 million tons per yr — the equal of taking 325,000 vehicles off the highway yearly.

First GE Haliade-X Turbine Put in at Winery Wind 1 Undertaking. Picture courtesy of Winery Wind.

All informed, the Winery Wind 1 undertaking will save clients $1.4 billion over the primary 20 years of operation.

Union Staff & the Winery Wind 1 Undertaking

An 806-megawatt undertaking situated 15 miles off the coast of Martha’s Winery and greater than 30 miles off the coast of Cape Cod, Winery Wind 1 will create 3,600 full time equal (FTE) job years. From the outset of this undertaking, Winery Wind acknowledged the significance of constructing and supporting a workforce of native, extremely expert, and numerous tradespeople.

In July 2021, Winery Wind signed the primary Undertaking Labor Settlement for an offshore wind undertaking within the US, which outlined the creation of 500 union jobs although the undertaking. As part of the Undertaking Labor Settlement, native union labor might be used each on the vessels and onshore on the New Bedford Marine Commerce Terminal. The undertaking estimates that roughly 400 union members have labored on the undertaking thus far. Foss Maritime, a US service contractor that gives union jobs for its workers, has partnered with DEME Offshore US to design and construct extremely specialised US-flagged barges to move the parts to the lease space.

Winery Wind is a three way partnership between Avangrid, Inc. and Copenhagen Infrastructure Companions. Avangrid CEO Pedro Azagra famous, “We’re proud that native union labor will pioneer the set up of the huge GE generators that may harness the winds off the shores of Massachusetts.” The collaboration with union management is a mannequin of how the comparatively new offshore wind trade could be a responsive member of the communities it serves, making certain accessible and family-sustaining careers.

“It could look straightforward, however the secure transportation of those parts miles over the open water isn’t any small feat,” stated Winery Wind CEO Klaus S. Moeller. “Whereas we’ve had many firsts, as soon as this turbine is put in, it’s going to stand as a proud image of American’s power transition. I need to thank all of our companions for his or her continued collaboration and look ahead to celebrating the progress of our trade.”

Transporting the Parts to the Offshore Substation

Winery Wind started offshore building in late 2022, achieved steel-in-the-water in June, and accomplished the nation’s first offshore substation in July. Building flows by means of the New Bedford Marine Commerce Terminal.

The plan is for GE to load the US-flagged Marmac from the New Bedford Marine Commerce Terminal with 3 vertically positioned tower sections reaching greater than 200 toes in top, three 321-foot-long blades, and a nacelle pod that homes the producing parts. The Marmac in New Bedford, MA and Foss Prevailing Wind in Boston, each 400-feet-long, are the one two barges in existence able to transporting in an upright place GE’s huge Haliade-X turbine parts — which, when constructed, will rise greater than 700 toes.

GE Haliade-X turbine being shipped by boat. Picture courtesy of Avangrid.

Foss is liable for towing and feeding the parts to DEME’s Sea Installer building vessel. Sea Installer, which measures greater than 430 toes in size and 150 toes huge, is a heavy-lift jack-up crane vessel that hoists itself out of the water on legs which are over 300 toes in size. As soon as elevated, the vessel turns into a platform the place the just lately upgraded crane, now able to lifting greater than 1600 tons, can set up the tower sections, nacelle, and blades for every WTG.

These are the one two barges on the planet able to transporting the parts. They’re fitted with a movement compensation system that stabilizes the upright towers in ocean circumstances. The barges make the most of a specifically designed Barge Grasp expertise that makes use of a patented management system and cylinders that help a platform and actively compensate the motions of the barge. The wind turbine parts are mounted to the movement compensated platform for a easy experience in ocean circumstances.

“The profitable meeting of the primary Wind Turbine Generator represents an essential undertaking milestone and one other historic first for our port,” stated New Bedford Mayor Jon Mitchell. “It additional demonstrates New Bedford’s capability to help the staging of main wind initiatives.”

Copenhagen Infrastructure Companions and Avangrid, Inc. introduced in late October that the Winery Wind 1 undertaking closed a first-of-its-kind tax fairness package deal for industrial scale offshore wind with three US-based banks. The $1.2 billion greenback funding transaction was reached with JP Morgan Chase, Financial institution of America, and Wells Fargo, making it the most important single asset tax fairness financing and the primary for a industrial scale offshore wind undertaking.

“Closing on a tax fairness package deal has at all times been a central aspect to reaching monetary success for the first-of-its-kind Winery Wind 1,” stated Tim Evans, companion and head of North America for CIP. “With this funding, Winery Wind 1 strikes Massachusetts nearer to its aim of decreasing greenhouse fuel emissions by 50% by 2030.”

Need to see the work in motion? Right here’s a Foss Offshore Wind video.

Ultimate Ideas

Whereas some wind and different renewable power initiatives are stumbling quickly, a rising public pattern towards the significance and acceptance of wind and different renewable power sources throughout all areas of the US is going down. The success of the Winery Wind 1 first tower set up is a big step towards President Joe Biden’s clear power initiatives — the Biden administration just lately accepted a plan to put in as much as 176 wind generators off the coast of Virginia.

The Departments of the Inside and Power launched An Motion Plan for Offshore Wind Transmission Improvement within the US Atlantic Area, a set of actions that may catalyze offshore wind power, strengthen the home provide chain, and create good-paying, union jobs. It outlines fast actions wanted to attach the primary era of Atlantic offshore wind initiatives to the electrical grid in addition to long run efforts to extend transmission over the subsequent a number of many years.

The following step might be for extra monetary establishments to help these offshore wind endeavors for the lengthy haul fairly than in response to quick time period financial points.