New England Offshore Wind Public sale Attracts 4 Bidders


4 builders have submitted their bids in response to the mixed Connecticut-Massachusetts-Rhode Island offshore wind solicitation with the tenders totalling 6.8 GW. The proposals have been made by Avangrid Renewables, Ørsted, SouthCoast Wind Power, and Winery Offshore.

In October 2023, the three states signed a Memorandum of Understanding (MoU) to collaborate on offshore wind procurement, though every held its personal tender.

Massachusetts launched its fourth and largest offshore wind solicitation up to now on 30 August 2023, searching for 3.6 GW of latest era capability, and Rhode Island and Connecticut opened their offshore wind solicitation in October 2023 for 1.2 GW and a couple of GW of offshore wind, respectively.

Massachusetts obtained bids from Avangrid Renewables, SouthCoast Wind Power, and Winery Offshore in response to the area’s largest solicitation up to now for as much as 3,600 MW of offshore wind.

“The Healey-Driscoll Administration will evaluate bids over the approaching months, and coordinate with Connecticut and Rhode Island to judge multi-state tasks that might enhance advantages for the area, decrease prices, and improve venture viability,” mentioned Elizabeth Mahony, Massachusetts Power Sources Commissioner.

Remaining selections on venture analysis are due by 7 August. The electrical distribution corporations would then execute long-term contracts with chosen venture(s) by 9 October, and ensuing contracts can be filed with the Massachusetts Division of Public Utilities for evaluate and approval by 13 November.

Rhode Island Power introduced on 27 March that it’s going to consider offshore wind proposals from 4 venture builders that are Avangrid Renewables, Ørsted, SouthCoast Wind Power, and Winery Offshore.

Analysis of the proposals is predicted to take roughly three months, at which period Rhode Island Power will decide whether or not to maneuver ahead with contract negotiations.

Avangrid Submits A number of Proposals

Iberdrola’s Avangrid Renewables submitted a number of offshore wind proposals, together with the shovel-ready 791 MW New England Wind 1 (previously often called Park Metropolis Wind) and the 1,080 MW New England Wind 2.

Positioned 30 miles (about 48 kilometres) south of Barnstable, Massachusetts, within the federal lease space OCS-A-0534, New England Wind 1 obtained a Remaining Environmental Impression Assertion from the Bureau of Ocean Power Administration (BOEM) in February 2024, with a File of Choice (ROD) anticipated in April and Development and Operations Plan (COP) Approval anticipated in July this 12 months.

The venture building may begin as quickly as subsequent 12 months and obtain industrial operations in 2029, mentioned Avangrid.

New England Wind 2, formally often called Commonwealth Wind, is just supplied as a mixed venture with New England Wind 1. The venture may create as much as 9,200 full-time equal jobs and convey USD 8 billion in direct funding to the area.

Ørsted Proposes 1,184 MW Offshore Wind Undertaking

In a separate bid, Ørsted has proposed the 1,184 MW Starboard Wind offshore wind venture, which might energy greater than 600,000 houses within the state and convey practically USD 420 million of direct funding and expenditure to Connecticut.

Starboard Wind would end in greater than 800 full-time equal positions, together with many new jobs at New London’s State Pier.

Ørsted and Eversource are at the moment constructing the 704 MW Revolution Wind, Connecticut’s first offshore wind farm.

Winery Offshore Unveils Plans for Winery Wind 2

Winery Offshore proposed the 1,200 MW Winery Wind 2 offshore wind venture in response to the New England states’ solicitation for as much as 6.8 GW of offshore wind capability.

Winery Wind 2 can be positioned 29 miles (approx. 46 kilometres) south of Nantucket in lease space OCS-522, held by funds managed by Copenhagen Infrastructure Companions (CIP).

The corporate behind Winery Wind 1, the nation’s first commercial-scale offshore wind venture, mentioned that Winery Wind 2 would produce sufficient energy to produce greater than 650,000 houses.

The venture is predicted to generate approx. USD 2.3 billion in direct expenditure and will begin in 2031.

In relation to SouthCoast Wind, the corporate solely confirmed its bid, unveiling no particulars in regards to the offshore wind venture.

“Right this moment marks a pivotal second for the SouthCoast Wind venture and the offshore wind business in New England. The primary ever tri-state offshore wind solicitation demonstrates an unshakeable dedication to a clear vitality future for all and we’re proud to submit our bid,” mentioned Michael Brown, CEO of SouthCoast Wind.

After years of extraordinary work by our group, the SouthCoast Wind venture is on schedule to ship considerable and renewable energy to New England’s electrical grid by 2030.”


ADVERTISE ON OFFSHOREWIND.BIZ

Get in entrance of your audience in a single transfer! OffshoreWIND.biz is learn by hundreds of offshore wind professionals every day.

Observe offshoreWIND.biz on:

Related Articles

Latest Articles

Verified by MonsterInsights