0.9 C
New York
Saturday, December 21, 2024

First Metal Minimize for RWE’s Nordseecluster A Offshore Substation


The primary metal has been minimize for RWE’s Nordseecluster NC 2 offshore substation which is being constructed by Atlantique Offshore Vitality, the marine vitality enterprise unit of French firm Chantiers de l’Atlantique.

Chantiers RWE Nordseecluster NC 2
Picture Supply: Chantiers de I’Atlantique through LinkedIn

The Nordseecluster might be constructed in two phases, Nordseecluster A and Nordseecluster B, every comprising two offshore wind farms.

The websites of Part A (the 225MW NC 1 and the 435 MW NC 2) are at present within the allow software section. RWE was awarded the contract by the Federal Community Company for the 2 sub-areas of Part B (the 420 MW NC 3 and the 480 MW NC 4).

The steel-cutting milestone passed off ten months after RWE introduced the order to Atlantique Offshore Vitality for 2 substations for the Nordseecluster A wind farms.

The corporate was chosen to design, assemble, set up, and fee the offshore substations for the primary section.

The substation jackets might be constructed by Italy-headquartered Rosetti Marino beneath a contract signed with Chantiers de l’Atlantique in September 2023.

YOU MIGHT ALSO LIKE

Positioned 35 kilometres north of Juist Island and 55 kilometres off the German Coast, the Nordseecluster A offshore wind farms will comprise a complete of 44 Vestas 15 MW wind generators and are scheduled for industrial operation in early 2027.

The second section Nordseecluster B will add 900 MW of capability put in throughout two extra wind farms. Nordseecluster B is scheduled for commissioning in 2028/2029.


ADVERTISE ON OFFSHOREWIND.BIZ

Get in entrance of your target market in a single transfer! OffshoreWIND.biz is learn by hundreds of offshore wind professionals day by day.

Observe offshoreWIND.biz on:

Related Articles

Latest Articles

Verified by MonsterInsights