Adjudicating Change In Regulation: The CERC’s Determination On ISTS Costs And Its Impression On Renewable Vitality Tasks


Studying Time: 2 minutes

In a notable resolution by the Central Electrical energy Regulatory Fee (CERC) dated March 27, 2024, a fancy authorized matter involving Scatec India Renewables One Personal Restricted (SIROPL) and a number of other respondents, together with the Photo voltaic Vitality Company of India Restricted, GRIDCO Restricted, and the Ministry of New and Renewable Vitality, was addressed. This case sheds gentle on the intricate interaction of legislation, coverage, and contractual agreements within the renewable vitality sector.

SIROPL, an entity created to develop a wind energy challenge, discovered itself entangled in an internet of regulatory and coverage modifications. On the coronary heart of the dispute was the Ministry of Energy’s (MoP) order, which launched restrictions on the waiver of Inter-State Transmission System (ISTS) costs, pivotal for the challenge’s financial viability. SIROPL argued that this constituted a “Change in Regulation” underneath the phrases of its Energy Buy Settlement (PPA), affecting its challenge completion timeline and monetary obligations.

The challenge, which aimed toward establishing a 300 MW wind energy facility, was part of India’s bold efforts to spice up renewable vitality capability. The federal government, to encourage funding on this sector, had beforehand supplied waivers on ISTS costs for transmitting electrical energy via the inter-state transmission programs generated from photo voltaic and wind sources. This coverage was instrumental in mitigating transmission prices for renewable vitality builders, thereby fostering progress within the sector.

Nevertheless, the MoP’s subsequent orders, particularly the one dated November 23, 2021, launched limitations on the waiver of ISTS costs, straight impacting initiatives like SIROPL’s. The order said that the waiver would solely apply to initiatives commissioned as much as June 30, 2025, with additional restrictions on extensions because of pressure majeure or authorities company delays.

SIROPL’s plea to the CERC was multifaceted. It sought recognition of the MoP’s order as a “Change in Regulation”, thereby entitling it to compensation for delays past the waiver interval of ISTS costs. Moreover, it highlighted the challenges posed by the unavailability of the GSS (Grid Sub-Station), a crucial element for the challenge’s connectivity and operationalization.

The CERC, in its deliberation, needed to stability the ideas of contract sanctity with the dynamic nature of coverage and regulation within the vitality sector. It emphasised the significance of clear and honest regulatory practices to make sure the sustainable improvement of renewable vitality in India. The choice underscored the fee’s function in adjudicating disputes that come up within the quickly evolving vitality panorama, reaffirming its dedication to fostering an atmosphere conducive to progress whereas defending the pursuits of all stakeholders concerned.

This case exemplifies the complexities inherent within the renewable vitality sector, the place coverage shifts and regulatory choices can considerably influence challenge economics and timelines. It highlights the necessity for a nuanced understanding of the authorized frameworks and agreements that govern these initiatives, underscoring the significance of regulatory readability and stability in attracting and sustaining funding in renewable vitality.

Please view the doc right here for extra particulars.