British grid haunted by ‘phantom’ energy tasks holding again inexperienced targets



“Phantom” energy tasks that lack the cash and land rights to proceed are clogging up an already massively oversubscribed queue for the British electrical grid, says Centrica, after a report it commissioned discovered that is hurting the UK’s inexperienced targets.

“Lately vitality safety has rightly moved up the agenda as international locations look to safe provides and drive the transition to web zero,” mentioned Chris O’Shea, CEO of vitality providers firm Centrica, which owns British Gasoline.

“That’s why it defies perception that the queue for brand new, inexperienced vitality connections is blocked by ‘phantom’ energy tasks.”

“Not solely do these ‘builders’ not have the cash to develop,” he mentioned “many additionally don’t even have planning permission or land rights – they’re playing that holding an area within the queue will make them wealthy.”

His feedback come as Centrica in the present day (Tuesday) revealed a report it commissioned from consultancy Charles River Associates on the queue for the electrical grid in Nice Britain and what may be finished to enhance it.

The report comes as UK authorities vitality regulator Ofgem prepares to resolve subsequent month on learn how to streamline the queue.

Article continues under the advert

The present system for connecting new tasks to the grid was designed for including a “small variety of massive fossil gas turbines connecting annually,” discovered the report.

“With the speedy proliferation of renewable vitality tasks,” it mentioned the present queue is between three and 4 occasions oversubscribed – a state of affairs that has turn into “considerably worse in the previous couple of years.”

The report discovered there are presently 371GW of tasks on this queue, with round 166GW of those as a consequence of be linked by 2030.

Round 114GW value of tasks have listed their connection date as earlier than 2029, however round 62GW of these tasks are “nonetheless within the scoping section” and should not even have secured land rights or planning consent.

The longer queue and watch for connections “will increase uncertainty for builders,” the report argued. It discovered that there are not any obtainable websites to attach technology in South Wales, North Wales, the North West or the South West earlier than 2036.

This has a “damaging impact” on the investments required to satisfy the UK’s web zero targets, it mentioned.

Ofgem is presently deciding on whether or not to rectify these points by handing Nationwide Grid ESO, the transmission system operator in Nice Britain (however not Northern Eire), the facility to terminate agreements to attach tasks in the event that they miss key milestones.

Ofgem is weighing whether or not to use this proposal to tasks which might be already within the queue or solely to new or modified tasks.

The report mentioned that solely making use of it to new tasks would have “restricted impact” as a result of massive variety of delayed tasks within the present queue.

At the moment, the report discovered that 12.3GW of photo voltaic, onshore wind and storage tasks anticipated to attach by 2029 are “unlikely to attach directly.”

They’d due to this fact danger being terminated if the proposal was utilized to present tasks.

O’Shea mentioned that “fortunately Ofgem has now recognised the necessity for motion however each day we watch for motion is costing customers cash.”

He mentioned that “urgently introducing” rule adjustments and making use of them to the present queue in order that “phantom tasks lose their place” would present that Ofgem helps cut back prices for customers, drive the vitality transition and enhance the UK’s vitality safety.