Ijen geothermal energy plant in Indonesia targets 2024 COD



Drilling begin at Ijen challenge, East Java, Indonesia (supply: Medco Energy)

The 34-MW Ijen Unit 1 geothermal energy plant in East Java, Indonesia by Medco Cahaya Geothermal is focusing on industrial operations by the top of 2024.

The 34-MW Section 1 growth of the Ijen geothermal energy plant in East Java, Indonesia being developed by PT Medco Cahaya Geothermal (PT MCG) is focusing on industrial operations by the top of 2024. Development work for the challenge is ongoing, a part of which is a 150 kV transmission line from the ability plant to the PLN substation over a distance of about 28 kilometers.

“Development is in keeping with plan. We try to start out working the Blawan Ijen Geothermal Energy Plant by the top of December,” stated Senior Supervisor Exterior Relations of PT Medco Cahaya Geothermal Ibnu Nurzaman

The Ijen geothermal challenge has had a protracted historical past, having secured a PPA with PT PLN again in 2013. Philippine-based Aboitiz Energy withdrew from a possible three way partnership with developer Medco Energy in 2017, earlier than Ormat Applied sciences finally acquired a 49% stake within the challenge to formally discovered PT MCG. In 2022, the three way partnership was given approval by the Ministry of Vitality and Mineral Assets to drill a collection of manufacturing and injection wells on the web site.

PT MCG has been profitable in elevating funding for the challenge by means of the current years. In 2023, PT MCG signed a Financing Settlement with PT Sarana Multi Infrastruktur (Persero) (SMI), a Particular Mission Car beneath the Indonesian Ministry of Finance. The challenge as soon as once more obtained a $126 million mortgage from the U.S. Worldwide Improvement Finance Company (DFC) in early 2024.

In early 2023, PT MCG additionally signed an EPCC contract with PT Inti Karya Persada Tehnik (IKPT) and consortium associate PT Multi Fabrindo Gemilang for the Ijen Unit 1 geothermal energy plant.

A complete of 83 tower items can be wanted for the ability transmission system connecting the Ijen energy plant to the PLN substation, of which 78 had already been erected. In line with Aditya Negara, Head of Geothermal at PT MCG, 37 of the towers are situated on personal land whereas the remainder are in forest areas. For towers inbuilt personal land, the developer had to supply compensation to the homeowners.

The Ijen geothermal energy plant is a part of the 10-year Electrical energy Provide Enterprise Plan (RUPTL) of PT PLN. Electrical energy generated from the ability plant can be equipped to each the islands of Java and Bali.

Supply: Detik Jatim and IKPT