Main Midwest Transmission Challenge Secures Closing Siting Approval


The Missouri Public Service Fee (MPSC) has accepted Invenergy’s request to amend its present certificates of comfort and necessity for the 800-mile Grain Belt Specific: an electrical transmission infrastructure mission that can assist transfer wind energy by way of Kansas, Missouri and Illinois.

Invenergy says the choice is the final required state siting approval for vital enhancements to the mission and gives the mandatory certainty about energy supply to assist ongoing and upcoming industrial contracting efforts.

Approvals secured this 12 months from state regulatory commissions authorize Grain Belt Specific to be financed and constructed in two phases. The mission has acquired 95% of easements for the Part 1 predominant line, between southwest Kansas and northeast Missouri.

Invenergy is rising the road’s capability to five GW, with 2.5 GW flowing to the road’s mid-point supply location in Missouri – a fivefold enhance in native supply in comparison with the sooner mission design.

“We’re witnessing a worldwide, long-term and complete motion towards renewable vitality,” the MPSC’s order acknowledged. “The vitality on the mission gives nice promise as a supply for inexpensive, dependable, secure and environmentally pleasant vitality that can enhance resiliency of the grid.”

“Securing the mandatory state regulatory approvals is one other essential step towards Grain Belt Specific bringing decrease electrical payments and better reliability to shoppers in Missouri and throughout the Midwest,” mentioned Shashank Sane, govt vice chairman and head of transmission at Invenergy. “We thank the state leaders in Kansas, Missouri and Illinois who’ve thoughtfully thought-about the super advantages of Grain Belt Specific.”

Additionally this week, the Federal Power Regulatory Fee (FERC) acknowledged a request by Grain Belt Specific to provoke a brand new open solicitation course of to contract energy supply on Part 1 of the road. As a service provider transmission mission, Grain Belt Specific enters into voluntary contracts for energy supply. The method, which might begin as early as this 12 months, could be supported by an impartial advisor to help in evaluating bids. In Missouri, 39 communities are already contracted for energy supply from the road from a previous open solicitation.

Grain Belt Specific milestones which have taken place within the final 12 months embrace the next:

  • In December 2022, the U.S. Division of Power started the federal environmental assessment for Grain Belt Specific Part 1;
  • In January, Grain Belt Specific chosen Siemens Power Inc. to produce the high-voltage direct present transmission expertise for Part 1 of the mission;
  • In March, the Illinois Commerce Fee granted Grain Belt Specific its certificates of public comfort and necessity;
  • In April, Invenergy Transmission introduced a long-term provide settlement with Prysmian Group North America for as much as 12,500 miles of overhead conductor cable by way of 2029 to produce Grain Belt Specific and different initiatives;
  • In June, the Kansas Company Fee granted an amended approval of the Grain Belt Specific transmission mission to permit for phasing.

Grain Belt Specific is focusing on to start full development as quickly as the beginning of 2025, pending federal allowing approvals.