18.5 C
New York
Thursday, May 9, 2024

Prysmian Completes Neart na Gaoithe Cabling Job Offshore Scotland


Italy-headquartered Prysmian has concluded the set up of submarine and land energy cables to attach the 450 MW Neart na Gaoithe offshore wind farm to the Scottish mainland energy grid.

The offshore wind venture is now within the testing and commissioning section and the system is scheduled to go stay throughout 2024.

Prysmian designed, provided, and put in two HVAC 220 kV three-core extruded export submarine cables with single-wire armoring which attain land at Thorntonloch seaside in East Lothian.

The corporate additionally offered two 220 kV extruded land cable circuits that hyperlink the landfall space to the substation at Crystal Rig and two 400 kV extruded land cable circuits to hyperlink the Crystal Rig substation to a Scottish Energy substation.

“Prysmian managed complicated scopes such because the sea-land cable touchdown, the laying and burial of the cables, the pulling of the cables onto the offshore platform and the termination of the cables all inside its scope. This required main effort spent on interfacing with different packages engaged on the venture,” stated Lubna Gemey, Challenge Supervisor for the offshore actions.

The submarine cables have been manufactured at Prysmian’s heart of excellence in Pikkala, Finland, whereas the land cables have been produced in Gron, France.

The marine cable laying work was carried out by the corporate’s Cable Enterprise vessel, whereas the burial marketing campaign was carried out by the Normand Pacific.

The Cable Enterprise additionally managed the pulling of the cables on the platform.

“We’re proud to have delivered the venture matching the required high quality however most of all reaching the heaviest potential well being and security outcomes, with 0 LTI (misplaced time harm) registered in over 600,000 labored manhours,” stated Massimo Galleta, Challenge Director.

Among the many challenges Prysmian encountered through the venture was the necessity to coordinate with many different corporations concerned, the agency stated.

The wind generators for Neart na Gaoithe are produced by Siemens Gamesa, the foundations are by Saipem, and the substations are provided by GE.

On the offshore platforms, we have been working in a confined area with the opposite contractors, ensuring that issues have been going easily, additionally contemplating the simultaneous operations that have been being carried out. This required sturdy planning to collaborate effectively and meet time necessities, a great angle, and shut cooperation,” stated Gemey.

“One other technical problem confronted by Prysmian through the venture was associated to the sea-land horizontal directional drilling (HDD), a 600 meter pipe put in on the sea-land transition space that allowed the cable to move from offshore to the land,” stated Galleta.

Prysmian employed a brand new technique for putting in the pipe, which was pushed from the shore as an alternative of being pulled from offshore, with a purpose to restrict the engagement of the offshore unfold all the time subjected to climate constraints.

Cable burial actions on the inter-array routes inside the Neart na Gaoithe offshore wind farm have been achieved in March 2024, following the completion of cable set up works in January.

Positioned 15 kilometres off the coast of Fife in Scotland, the 450 MW Neart na Gaoithe offshore wind farm will characteristic 54 Siemens Gamesa 8 MW wind generators.

The venture, owned by the three way partnership between EDF Renewables and ESB, is anticipated to provide its first energy this 12 months.


ADVERTISE ON OFFSHOREWIND.BIZ

Get in entrance of your audience in a single transfer! OffshoreWIND.biz is learn by 1000’s of offshore wind professionals day by day.

Observe offshoreWIND.biz on:

Related Articles

Latest Articles

Verified by MonsterInsights